Ivany Campus | May 2024
Category:
Construction updates
The 200-bed, 96,000 sq ft. student housing facility at Ivany Campus is on track to open in September 2025.
The latest process:
-
Roof work is now complete
-
The structural slab is in place
-
Interior framing and drywalling work continues
-
Mechanical and electrical rough ins work is progressing on schedule
-
Curtain wall is now 75% complete
-
Fireproofing is finished.