The 200-bed, 96,000 sq ft. student housing facility at Ivany Campus is on track to open in September 2025. The new housing offers a variety of 1-bedroom and 4-bedroom suites to students attending the campus. With lots of activity happening to complete the building, here’s a look at the latest progress on-site.

The latest updates:

  • Elevator installation is currently underway

  • Paving and flatworks throughout the building are now complete

  • Ceiling grid is up on floors 2, 3, 4 and 5

  • Flooring is being installed on floors 3, 4 and 5

  • Millwork is being installed on floors 3, 4 and 5

  • Mechanical systems are beginning testing this month