The 200-bed, 96,000 sq ft. student housing facility at Ivany Campus is on track to open in September 2025.

The latest process:

  • Roof work is now complete

  • The structural slab is in place

  • Interior framing and drywalling work continues

  • Mechanical and electrical rough ins work is progressing on schedule

  • Curtain wall is now 75% complete

  • Fireproofing is finished. 